Cogent Energy has designed and installed a state of the art tri-generation plant.
The tri-generation plant provides low CO2 emissions density electricity when compared to the grid.* It also delivers cooling for the building’s air-conditioning system. This helps to reduce Origin’s carbon footprint.
Building specifics
Building owner: Mirvac / ING
Location: 20 Bond Street, Sydney
Building description: Commercial complex – premium offices and retail space
Building size: 32 levels, 35,000 square meters
Tri-generation plant capacities
Operational date: 21st June 2011
Peak electrical: 601 kW at 0.8 power factor
Peak cooling: 660 kW
Energy efficiency:
80% overall efficiency (estimated)*
The Bond Street plant comprises of a 601 kW Jenbacher JMS 312 low NOx natural gas-fired engine that is connected in parallel to the grid.
This is connected with a single-double effect Broad absorption chiller to generate 660 kW of cooling, making full use of all engine jacket and exhaust heat. The absorption chiller is fully integrated into the building’s chilled and condenser water systems.
Benefits
Energy efficiency
5 star NABERS rating being targeted.
Getting multiple forms of energy from one fuel can result in an efficiency gain of up to 80% versus the grid average and compared to 38% for the best coal fired power station.*
Sustainability
CO2 Reduction – estimated savings of up to 1,200 tonnes of CO2 per annum.*
Backup
Provides emergency backup if grid connection fails. The plant is configured to operate either in grid parallel import or island mode and operates automatically during the peak and shoulder demand periods or during grid outages as emergency backup.